Practical completion inspections for WA new builds

What a practical completion or handover inspection is, when to book it, what is checked, and how it sits alongside the defects period and complaint time limits in Western Australia.

Published 23 November 2026. Last reviewed 23 November 2026.

A practical completion inspection (PCI) is a focused inspection of a new home near the end of construction, usually just before or around handover. It is carried out in accordance with the National Construction Code (NCC) and relevant Australian Standards for workmanship. It checks the visible work in safely accessible areas against those requirements and acceptable workmanship standards. The report records observed incomplete or defective items, workmanship concerns and damage, so you can discuss those findings with your builder. Inspection reports are delivered within 24 hours of the inspection.

The terms “practical completion inspection” and “handover inspection” are commonly used for the same kind of visit, but the exact purpose, timing and deliverables should be confirmed in the written engagement. Contract definitions of practical completion can differ. This inspection does not itself determine contractual practical completion, provide an occupancy approval, or certify concealed construction, unless a separate authority is expressly agreed.

When should I book?

Book a practical completion inspection before you collect the keys, once the proposed date and the builder’s access arrangements are known. Enquire as early as you can, because attendance depends on availability and a written agreement on scope.

Provide the property address, the builder’s contact for access, the planned handover or practical completion date, and any drawings, specifications or items already raised with the builder. A follow-up inspection can be discussed separately after the first report.

What is checked?

Within the agreed scope, the inspection checks the visible work against the NCC and relevant Australian Standards, and acceptable workmanship standards. It looks at workmanship and finishes in safely accessible areas, apparent damage and incomplete items at the inspection date, and, where agreed, comparison with relevant supplied plans and specifications. The report includes photographs, itemised observations, access limitations and recommended next steps.

Service commissioning and specialist testing are excluded unless expressly agreed. The inspection is not a substitute for a pre-purchase building inspection under AS 4349.1, and it is not a timber pest inspection under AS 4349.3. We do not provide legal advice about your building contract or statutory rights.

Practical completion and the defects period

In contracts to which the Home Building Contracts Act 1991 (WA) applies, it is a term of the contract that the builder is liable to make good, at the builder’s cost, defects in the home building work that are notified in writing to the builder within four months starting on the day of practical completion. The contract may provide a longer notification period, but not a shorter one under that implied term.

The same Act describes practical completion as the stage where the home building work is completed except for any omissions or defects which do not prevent the work from being reasonably capable of being used for its intended purpose. Your particular contract may also define practical completion and handover, including when final payment is due. Those are questions for your solicitor. A written defects list, prepared from a timely inspection, is a practical way to notify items to the builder within the period that applies to your contract.

The Building Services (Complaint Resolution and Administration) Act 2011

The Building Services (Complaint Resolution and Administration) Act 2011 (WA) is the legislation under which a person may complain to the Building Commissioner about a regulated building service not being carried out in a proper and proficient manner, or being faulty or unsatisfactory, and under which an owner or builder may also complain about certain home building work contract matters.

A building service complaint is generally out of time if it is made more than six years after the completion of the regulated building service. The date of completion is determined under the Act and the regulations. Where work is carried out under a building permit, completion is typically tied to the notice of completion (or a notice of cessation) given under the Building Act 2011. Where the work is not carried out under a permit, but is carried out under a home building work contract or other contract that provides for a date of practical completion and practical completion has been achieved, the regulations treat the service as completed on the date practical completion is achieved. Separate, often shorter, time limits can apply to home building work contract complaints. Official guidance also describes a preliminary “notice of proposed complaint” that is ordinarily given to the other party at least 14 days before a complaint is lodged.

These time limits and procedures are general. They can depend on the type of complaint, the contract and the facts. This guide is not legal advice. You should obtain legal advice promptly about your rights, notices and deadlines. The Building Commissioner’s processes, and any later referral to the State Administrative Tribunal, are determined under the legislation and are not a guaranteed outcome.

How to book

Request a quote or book online, agree the scope in writing, and confirm access with the builder. Online booking is available for practical completion inspections, as well as pre-purchase, timber pest and pre-settlement inspections.

The Building Inspector is a Registered Building Practitioner (WA) No. 101996, with 27 years of national and international industry experience. For service details, go to practical completion inspections in Perth. We do not provide legal advice.

Common questions

Questions about this guide.

What standards does a practical completion inspection use?

The inspection is carried out in accordance with the National Construction Code (NCC) and relevant Australian Standards for workmanship. It checks the visible work in safely accessible areas against those requirements and acceptable workmanship standards. It does not certify concealed construction, and it is not a substitute for a pre-purchase inspection under AS 4349.1.

Is a practical completion inspection the same as a pre-purchase inspection?

No, a practical completion inspection is a focused inspection near the end of a new build. It checks the visible work against the NCC and relevant Australian Standards, and acceptable workmanship standards, and records observed incomplete or defective items within the agreed scope. A pre-purchase inspection is a more comprehensive visual assessment under AS 4349.1, usually for a buyer before a purchase deadline. They are different services.

When should I book a practical completion inspection?

Book before you collect the keys, once the proposed date and the builder’s access arrangements are known. Enquire early, because attendance and report timing depend on availability and a written agreement on scope. Inspection reports are delivered within 24 hours of the inspection.

Does this inspection decide practical completion under my contract?

No, a practical completion inspection does not itself determine contractual practical completion, provide an occupancy approval or certify concealed construction, unless a separate authority is expressly agreed. The report records those findings, assessed against the NCC and relevant Australian Standards for workmanship, for you to discuss with your builder and, where needed, your legal advisers.