Home / Guides / Clarke Energy v Alinta [2026] NSWSC 1124
Recent landmark case · Contract administration

Clarke Energy v Alinta [2026] NSWSC 1124

A plain-English summary of this NSW Supreme Court decision about a Western Australian project, and what it means for contract administration and contract management in Perth and WA.

Published 24 November 2026. Last reviewed 24 November 2026.

On 21 September 2026, Justice Rees of the Supreme Court of New South Wales gave judgment for the contractor in Clarke Energy (Australia) Pty Ltd v Alinta Energy Transmission (Roy Hill) Pty Ltd [2026] NSWSC 1124. The official decision is published on NSW Caselaw: [2026] NSWSC 1124.

What was decided?

Clarke was engaged under a contract worth about $78 million to engineer and construct a gas-fired power station in remote Western Australia, at Newman. The contract was governed by Western Australian law. After delay on the project, Alinta sought liquidated damages at the contractual cap of about $7.8 million. Clarke claimed extensions of time, delay costs and a disputed variation.

The Court allowed extensions of time totalling 142 days and entered judgment for Clarke of $7,192,414 plus interest.

The reasons matter as much as the result. Clarke served its first extension of time claim on the principal, but omitted to copy the superintendent as the contract required. That omission was promptly corrected. The superintendent was supposed to determine the claim within 15 business days. It was ultimately determined almost two years later, and no extension was allowed. The Court held that Alinta had waived the right to rely on that procedural failure, because it later asked a superintendent to determine the claim on its merits.

The Court also held that Clarke owned the float in its program. An extension of time was available for delay to practical completion, but not simply to restore unused activity float. Delay costs described as “reasonable additional costs and expenses directly incurred” were held to include a usual margin for overheads and profit.

The project had three superintendents. The first became overwhelmed and made no determinations. The second privately indicated to Alinta that he was inclined to issue a certificate of practical completion, and was promptly replaced. The Court said that private communications between a superintendent and one party undermine the role, and that removing a superintendent to stop an unwanted determination effectively destroys that role. The Court rejected the claim that the superintendents owed Clarke a duty of care in negligence.

The Court also held that the prevention principle was not excluded merely because the contract contained an extension of time regime.

What it means for WA building owners, builders and contract administrators

This was a decision of the NSW Supreme Court, not a Western Australian court. It does not bind the Supreme Court of Western Australia, the State Administrative Tribunal, or other WA decision-makers. It is still likely to be treated as persuasive, particularly because the contract itself was governed by Western Australian law and the project was built in WA.

The practical lessons are the same whether you are a builder, a subcontractor, a home owner under a building contract, or someone administering the contract in Perth or elsewhere in Western Australia.

Keep notices, programs and daily records in order as the job proceeds. Follow the notice clause strictly, including who must be copied. Do not assume a court will later rescue a missed notice, even though, on these facts, a waiver argument succeeded. If you are the principal or superintendent, deal with claims in the time the contract allows, and keep the superintendent’s role independent. Replacing a superintendent to avoid an unwelcome decision can undermine the very process the contract relies on.

These issues often surface in Home Building Contract Disputes as well as in larger commercial jobs. Getting independent contract administration support early, while the records, program and notices can still be organised, is usually easier than trying to reconstruct the story after the date for practical completion has passed.

If a dispute later needs technical evidence, an Accredited Expert Witness (Resolution Institute) can prepare an independent report. That is a separate service from day-to-day contract management. We do not provide legal advice. Speak with your solicitor about your legal position.

Need help with contract administration or contract management?

If you are dealing with delay notices, extensions of time, variations or a building contract that is starting to go off track in Perth or Western Australia, get independent contract administration support early.

We help builders, contractors, subcontractors and owners keep notices, programs, variations and payment records organised, and prepare extension of time and delay claims that meet the contract. This is practical contract management support for commercial and home building contracts. It is not legal advice.

Call 0448 028 979 or email [email protected]. You can also request a quote for contract administration.

Common questions

Questions about this case.

Does this case bind courts in Western Australia?

No. It is a decision of the NSW Supreme Court, not a Western Australian court, so it does not bind the Supreme Court of Western Australia or the State Administrative Tribunal. It is still likely to be treated as persuasive, especially because the contract was governed by Western Australian law and the project was built in WA.

What does it say about extension of time notices?

Serve notices in the form, and on every person, the contract requires, and do it on time. In this case the contractor’s failure to copy the superintendent did not end the claim, because the principal was later held to have waived that objection. That is not something to rely on.

Who owns program float?

On the wording of this contract, the contractor owned the float. An extension of time was measured by delay to practical completion, not by days of activity float that had been used up.

Why does the superintendent’s independence matter?

The Court treated the superintendent’s independence as a working obligation, not a formality. Private communications with one party about a contentious determination, and replacing a superintendent to stop a decision you do not want, were found to undermine or destroy that role.

Is this legal advice?

No. This is a short general summary of a published judgment, not legal advice. Every contract and dispute is different. Speak with your solicitor about your own situation.

Perth & Western Australia

Get your contract administration organised.

If notices, delays or variations are already in play, call 0448 028 979 or email [email protected]. Scope, fee and availability are agreed before work begins.

Request contract administration ›
Request a quote ›